Havana Barge Unloading Facility

Kraemer installed a barge unloading facility as part of federally mandated upgrades to the Havana Power Station. The project included approximately 650 cubic yards of dredging, clearing/grubbing, installation of 310 wall feet of PZ 22 sheeting, double row of tie backs/whalers, two dead man walls, eight each rubber bumpers, and 7,800 tons of aggregate backfill which was brought in by barge.